If 5 workers can finish a task in 4 days, how many days will it take 10 workers to finish the same task?

  • 4 days
  • 5 days
  • 2 days
  • 10 days
  • c
  • 5 workers complete the task in 4 days ( It means total work 5*4=20)
    How many days are required to finish the same work by 10 workers?
    Days=Total Work / Total Workers
    Days=20/10=2